Water Supply Commission:
The last monthly BWSC meeting was held in High Bridge on May 21, 2007. A presentation was given to the elected leadership promoting the equity ownership regional model, but the primary focus was to explain the real need for State and Federal funding for the BWSC. The minutes (draft) of that meeting and a copy of the presentation have been provided on pages 20-30.
Key components of the presentation worth mentioning:
- Ultimate BWSC concept includes a Pool 3 KAW/BWSC plant (Phase 1) and a Louisville Water Company connection (Phase 2) for sources of potable water (“Two Rivers Solution”).
- “Without Assistance (financial)- Not Affordable”
PSC Case No. 2007-00134 (KAW’s Certificate of Convenience and Necessity to construct the proposed regional water treatment plant on Pool 3 and transmission line) continues to grow with more entities asking for intervention. In addition to those entities that have requested to intervene (AG, LFUCG, BWSC, KIUC, CAWS), the
Kentucky River
Authority has recently passed a resolution in support of the BWSC/KAW Pool 3 plant and has authorized it’s director to file a motion for full intervention.
|